U.S. Department
of Labor |
Mine Safety and
Health Administration Industrial Park Road RR1, Box 251 Triadelphia, West Virginia 26059 |
December 13, 1999
MEMORANDUM FOR LEE D. RATLIFF
Assistant District Manager, North Central
District
Metal and NonMetal Mine Safety and Health
FROM: ARLIE B. MASSEY
Electrical Engineer
SUBJECT: Executive Summary of Testing of Busbar from Kaiser
Aluminum And Chemical Company's Gramercy Plant
A series of eight dielectric tests were conducted on the phase "A" busbar that
was removed from the Auxiliary Cabinet of Switch House No. 2 at Kaiser Aluminum
And Chemical Company's Gramercy Plant. This busbar was involved in the phase to
ground fault that occurred at approximately 4:43am on July 5, 1999. The busbar
has two identifying numbers, PS-1 and PE 28. The purpose of the tests was to
determine whether the busbar was effectively insulated for 13,800 volt system
voltage. A total of eight tests were performed on the busbar at locations where
the insulation was not damaged by the electrical fault. Each dielectric test was
conducted by applying approximately 15,000 volts between the metallic bar and
the outer surface of the insulation. The voltage was increased from
approximately zero volts to approximately 15,000 volts at approximately 500
volts per second and maintained for approximately one minute.
Test Point | Maximum Test Voltage in Volts |
Failure |
---|---|---|
A | 15,200 | No |
B | 15, 200 | No |
C | 15,300 | No |
D | 15,300 | No |
E | 15,100 | No |
F | 15,200 | No |
G | 15,300 | No |
H | 15,200 | No |
In summary, insulation defects were not found during any of the eight tests. A
copy of the laboratory report is attached.
cc: John Radomski
M/NM, Arlington w/original Laboratory Report