DOE/RL-97-59
Revision 0
FINAL REPORT | JULY 26, 1997 |
ACCIDENT INVESTIGATION BOARD REPORT ON THE MAY 14, 1997, CHEMICAL EXPLOSION AT THE PLUTONIUM RECLAMATION FACILITY, HANFORD SITE, RICHLAND, WASHINGTON |
APPENDIX A
Memorandum for the Appointment of the Accident Investigation Board
APPENDIX B
Performance of Barriers
Table B-1. Performance of Barriers. | ||
Barrier | Purpose | Performance |
Concentration of Chemicals | Maintain chemical make-up specification for solvent extraction process | Barrier failed because the surveillance procedure did not require checking the chemical make-up specification; because the system was not designed for long-term storage. Therefore, the facility was operating in an un-analyzed condition. |
Standby Plan | Place PRF in safe configuration | Barrier failed because the standby plan did not address the cold chemicals in the Room 40 tanks, therefore the chemicals were stored long-term. |
PRF Room 40 long-term shutdown procedure | Place PRF Room 40 into safe configuration | Barrier failed because management did not use procedure, therefore the HN and HNO3 solution was not drained into plastic drums. |
Weekend Shutdown Procedure | Place PRF Room 40 into safe configuration for storage of chemicals during short term shutdown of solvent extraction process | Barrier failed because procedure limited storage to two weeks, therefore, the Facility line management violated the storage limitation requirement. |
Safety Authorization Basis | To operate the facility in a safe manner | Barrier failed because management did not conduct an unreviewed safety question screen. |
Lessons Learned | To prevent recurrence of events by providing feedback | Barrier failed because PFP line management failed to implement corrective actions from lessons learned from prior events involving HN and HNO3. |
Process Hazard Analysis | To define the safe operating parameters of the chemical process | Barrier failed because PFP line management did not initiate a hazards analysis for long term-storage of HN and HNO3 solution. |
Training Program | To train PFP engineers, operators, and managers to recognize potential hazards in the work place | Barrier failed because PFP training and qualification programs did not include lessons learned from prior events involving HN and HNO3 |
PFP Line Management | Maintain facility operations within the safety envelope | Barrier failed because PFP line management failed to implement the PRF Room 40 Long Term Shut Down Procedure, resulting in operations outside the safety authorization basis. |
RL Transition Projects Division Oversight | Ensure safe operation of PFP | Barrier failed because RL Oversight did not ensure that the lessons learned from the PUREX event were implemented at PFP. |
APPENDIX C
Change Analysis Chart
Table C-1. Change Analysis Chart
Factors | Accident Situation | Prior, Ideal, or Accident-Free Situation | Difference | Evaluation of Effect |
Explosion | Chemical reaction occurred in Tank A-109 | No chemical reaction | Reaction between HN and HNO3 | Gases/heat pressure/tank damage |
Historical practices | Training run suspended early | Normal system shutdown | Plant placed in shutdown from a different than normal status | Would have eventually implemented long term shutdown and no CCX would be present |
Historical practices | Long term shutdown not implemented | Long term shutdown would be implemented | Chemicals would have been removed from Tank A-109 | No explosion |
Historical practices | PRF left in Weekend Shutdown | Left in Weekend Shutdown for no more than two weeks | Plant did not implement long term shutdown after two weeks | Solution would not have been available to concentrate |
Exceeding authorization basis | Decision made to not immediately address PRF Room 40 chemicals results in long term storage in Tank A-109 | Long term shutdown of Room 40 | Long term storage of chemicals in Room 40 is outside of authorization basis | Allows chemical reaction resulting in explosion of Tank A-109 |
Lessons Learned implementation | Lesson Learned from PUREX 2BX event not fully recognized or implemented | Lessons Learned would have been recognized and implemented appropriate corrective actions | Corrective actions not taken to prevent concentration | Allows chemical reaction resulting in explosion of Tank A-109 |
Lessons Learned sharing | Lessons Learned from 1996 Savannah River event was judged by FDH Lessons Learned Committee to be not applicable to Hanford | Event would have been judged applicable and made available to Hanford facilities | Corrective actions not take to prevent concentration | Allows chemical reaction resulting in explosion of Tank A-109 |
Hazard analysis | Hazard recognition in FSAR does not identify any controls | Necessary controls identified in FSAR | Controls in plant Operating Procedures | No excessive concentration or long term storage in Tank A-109 |
Hazard analysis | No/inadequate hazard review of decision to store solution for future use | Performed USQ screen and associated hazard review performed prior to decision to store | Recognition of the hazard of storage | Implementing controls on storage |
APPENDIX D
Technical Aspects of the Accident
HN and HNO3 Background
Hydroxylamine nitrate (HN) is used in plutonium processes for the reduction of plutonium (IV) to plutonium (III) in water-diluted nitric acid (HNO3) solutions. Reduction of the plutonium valence from IV to III changes the plutonium from extractable in organic to inextractable in organic allowing the plutonium to be separated from impurities present in the organic feed solution. The HNO3 is present to prevent plutonium from polymerizing, which would create criticality hazards.
In the PRF process, dilute HN and HNO3 are mixed in a solution. The HN and HNO3 solution is prepared in Tank A-109 in Room 40 of the PRF. The HN and HNO3 solution is automatically fed to tank 30 in the PRF canyon by a level control system on Tank 30. Tank 30 is the HN and HNO3 solution feed tank for the complexant concentrate column.
A typical batch of HN and HNO3 solution contains 3,000 pounds of solution, which is what the volume of the tank will allow. In preparation for makeup the operator subtracts any solution heel weight from 3,000 pounds and gives that information to the engineer. The engineer then provides the operator with the makeup quantity to get a 3,000-pound HN and HNO3 solution batch. At the time of makeup, the operator takes Tank A-109 off-line to prevent an incomplete batch of HN and HNO3 solution from reaching tank 30. The operator then adds the amount of water, HNO3, and HN (in that order) prescribed by the engineer. The HNO3 used is identified as CAS, which is 1.5 M nitric stored in Tank A-108. The HN is 18 wt % HN as pumped from the vendor drum. The batch is sampled and results verified and tank is placed on-line.
Evaporation Mechanism
Tank A-109 was equipped with a 1-inch overflow line that discharged to a basin below the tank, and a 1-inch vent line that connected to a ventilation header exhausting to the 291-Z-1 stack. The vent header links all of the chemical preparation tanks in Room 40 to the E-3 exhaust duct, which eventually ends up in the Building 291-Z exhaust train and out the 291-Z-1 stack. No valving exists on either the overflow line, the vent line, or the vent header; thus, a continuous air flow path from Room 40 through Tank A-109 to the vent header existed in Tank A-109.
The continuous air flow through Tank A-109 was estimated at between 2 to 5 standard cubic feet per hour. This air flow is sufficient to evaporate several pounds per day of water in Tank A-109. The observed weight loss averaged 1.3 pounds per day (see Figure 3). The evaporation of water from Tank A-109 during a 4-year period slowly increased the concentration of the remaining HN and HNO3. For purposes of analysis, it is conservatively assumed that the weight-loss observed in Tank A-109 during the storage period is primarily a result of water evaporation, thus the HN and HNO3 remained essentially the same from the time the HN and HNO3 solution was mixed until the explosion.
Reaction Chemistry
On May 14, 1997, the concentrations of HN and HNO3 in Tank A-109 exceeded those necessary to initiate an autocatalytic reaction. This rapidly propagating reaction converted the concentrated chemical solution onto gases, water vapor, and heat. The available vent and overflow connections were not adequate to relieve the pressure increase with the result that the tank internal pressure quickly exceeded the design capability of the atmospheric tank.
Laboratory experiments and other research data indicates that concentrated HN and HNO3 aqueous solution will undergo autocatalytic reactions. The specific concentrations of the reactants depends on the temperature of the solution and the presence of a metallic catalyst. The reaction is rapid and results in the evolution of gases and heat. The reaction products are nitrogen, nitrous oxide, oxides of nitrogen, and water vapor.
The Board reviewed several autocatalytic reaction events experienced at the Savannah River and Hanford sites. The events are summarized in Table D-1. These reactions occurred at a wide range of chemical concentrations. The Board could not adequately define a safety envelope for indefinite storage of these chemicals.
Table D-1. Summary of Reaction Events.
Date | Location | Cause | Reported Chemical Concentration | Result |
9/19/68 | Hanford, PRF, Tank A-119 | Procedure violation resulting in 12 M HNO3 being added to dilute HN solution | HN 1.3 M HNO3 0.15 M |
Tank pressurized blowing solution out of chemical add port |
Early 1970s | Hanford, PRF, Tank A-109 | Procedure violation resulting in use of Tank A-109 for make up of high acid flush instead of in a separate tank | Unknown | Tank pressurized, blowing chemical add port lid off of tank and indenting the ceiling |
9/26/72 | Savannah River, F Canyon, HAW Evaporator | Sudden chemical decomposition during evaporator operations | HN 0.1 M HNO3 1.0 M |
3,000 liters of solution expelled from tank |
2/14/80 | Savannah River, F Canyon, Tank 5D | Failed steam valve concentrates solution in Tank 5D | HAS* 3.0 M HNO3 6.4 M |
Rapid pressurization causes elbow to fail |
12/3/89 | Hanford, PUREX, 2BX Pipeline | Solution isolated between two valves and decomposes | HN 0.7 M HNO3 1.6 M HY** |
Valve gasket fails |
12/28/96 | Savannah River, F Canyon, Tank 5D | Strong nitric acid HN solution heated by adjacent tank | HN 0.1 M HNO3 4.5 M |
2,500 pounds of solution spilled to sump |
*Hydroxylamine
Sulfate **Hydrazine |
Mechanical effects of an Autocatalytic Chemical Reaction
Analysis of the incident indicates that the chemical reaction that took place would have generated a rapid (3-4 second) buildup of pressure of several hundred psi inside Tank A-109. A pressure of 200 psi exerted on a 4 foot diameter lid would generate over 350,000 pounds of force on the lid. The tank lid was 3/16-inch stainless-steel flat plate with stiffeners and twenty-eight 5/8-inch stainless-steel studs. Three failed bolts were recovered. Visual observations of the three bolts show little plastic deformation (see Exhibit A-1).
Exhibit A-1. Recovered Bolts from Tank A-109 Lid.
Five bolts were observed to have remained in the tank flange, and the tank lid has five corresponding tears where tank bolts sheared through the tank lid. It appears that once the bolts opposite of the ones that remained failed, the lid folded over the remaining bolts, pulling the bolts through the holes in the tank lid. The deformation of the lid stiffeners (metal ribs on the underside of the tank lid) tends to confirm this observation. Calculations estimate the pressure in the tank that was necessary to shear the bolts through the tank lid to be between 150 and 250 psi.
Calculations show that the cylindrical portion of the tank should be able to withstand a pressure of between 400 and 750 psi without failing. This is consistent with the observations of the tank; the cylindrical portion of the tank did not fail. The bulge on the bottom of Tank A-109 could not be measured accurately, but was estimated to be approximately a 1- to 2-inch deformation using a corner of the tank as a point of reference. Finite element calculations indicate a pressure of between 200 and 300 psi would be consistent with a 1- to 2-inch deformation of the tank bottom.
Estimating the potential gas/heat generated by the reactions and released to Room 40, a resultant room pressure of up to 2 to 3 psi would be potentially available to act on the walls of Room 40. The north, west, and south walls are 7-inch concrete walls. The east wall is sheet metal partition with three sets of interior doors (953/954/955) for entry into Room 40. The damage to the interior doors (and windows in the doors) is consistent with what would be predicted for a 2 to 3 psi pressure surge in the room. The east wall of room 41 (south of Room 40, connected by corridor 47), also sustained damage. The pressure to which the east wall of room 41 was exposed was less than the pressure inside Room 40. The positive pressure inside Room 40 would quickly dissipate as the air flowed into the corridors and stairwell and was ultimately exhausted by the building ventilation system.
The damage to the lid, bolts, tank and room is consistent with the generation of gases and heat that was predicted by the chemistry of the reaction.
APPENDIX E
References