Record Number: 2063
CIS Descriptors: INSTALLATION OF PIPE SYSTEMS
MANUFACTURING INDUSTRIES
BURSTING

FATALITY REPORT



REPORT CHARACTERISTICS:

DONOR: Office of the Chief Coroner
JURISDICTION: Ontario
REPORT TITLE: Verdict of Coroner's Jury
INDIVIDUAL PRESIDING: Dr. C. R. Meyer, Coroner
PLACE OF INQUIRY: Frontenac County
DATE OF INQUIRY : 1988-05-25

INFORMATION ABOUT DECEASED:

NAME: Egan B. Holterman
OCCUPATION: Pipefitter
INDUSTRIAL SECTOR: Metal Manufacturing

ACCIDENT INFORMATION:

DATE OF FATALITY : 1987-12-07
PLACE OF ACCIDENT: Kingston Alcan Works North Plant
BRIEF CAUSE OF DEATH: Exsanguination; ruptured aorta; multiple internal
injuries; laceration of the liver and spleen.
BRIEF MANNER OF DEATH: Explosion: hit by eight inch pipe in the chest.
ACCIDENT DESCRIPTION:
Kingston Alcan Works was comprised of several plants. The plants of
concern to us in the present investigation are the North plant and the
South plant. Closure of the South plant took place in April 1987.
These plants were connected by a pipe line which carried compressed air
from the North plant to the South plant. It is an above ground, eight
inch aluminum pipe line which is under pressure 90 to 100 pounds per
square inch of compressed air.

The 7th day of December 1987 this line was still live even though the
South plant was closed, because it was necessary that new boilers and
air compressors had to be installed in the North plant. They were
finally commissioned on November 1, 1987.

On Thursday, December 3, 1987, Mr. James Latimer, the Contractor
Engineer at Alcan, decided the eight inch pipe line was no longer
needed. He advised Mr. Walter Hodgins, the Central Maintenance
foreman, that he could shut off the compressed air supply to the South
plant complex. This could be done safely by:

1) Shutting off the compressed air supply to the line by closing the
valve at the North plant.

2) Bleed off the air which was locked in the eight inch line.

3) Separate the pipes and install the cap.

It was decided that the person who should do the job would be Egan
Holterman.

Egon Holterman, 51 year old pipefitter, had worked for Alcan for
approximately twelve years. It was felt that he would have as much
knowledge about the workings of the pipe lines as anyone in the
Kingston plant.

Shortly after 2:00 pm on December 7, 1986, Mr Frank Maloney, a
Stationary Engineer at Alcan, met Mr. Holterman in the North plant to
assist him with the job. Mr. Maloney used a ladder to climb to the
shut off valve just outside the North plant. The valve was hard to
turn because it had been in the open position for a long time.

Mr. Holterman and Maloney then proceeded to the area of the pipe line
where the blank was to be installed. Mr. Holterman sprayed WD-40 on
the flange bolts which held the pipes together and at which joint the
blank was to be inserted. He then moved to the next joint, which was
one side of the expansion joint, which in this pipe line is shaped like
a U. He loosened the nuts and bolts on the flange but nothing
happened. Mr. Maloney reached to get a hammer from the tools, and as
he did so, there was a loud explosion.

As a result of this explosion Egon Holterman was struck by the eight
inch pipe in the chest. He was rushed to the hospital, and died on the
OR table.

RECOMMENDATIONS ISSUING FROM INQUIRY:

1. This jury agrees with the recommendations submitted by management,
Union and Department of Labour as stated in Exhibit 5 and would
recommend immediate implementation.

2. Appoint an in-plant safety coordinator to ensure that safety procedures
are followed at all times. Such procedures to include proper
job-related safety requirements.

3. We also recommend colour-coding as to content, of all piping systems in
conjunction with recommendation no. 5, page. 5.

Alcan Recommendations

Recommendations to change equipment, safety rules and operating procedures
all aimed at reducing or eliminating the possibility of repeating this
accident were submitted both by members of the accident investigating
committee and by other innovative, safety conscious Alcan employees. These
recommendations are as follows:

1. Communicate to all tradesmen the hazards of stored energy particularly
those associated with compressed gases. Dupont and Alcan Oswego will
be contacted for safety programs concentrating on stored energy.

2. Re emphasize the requirement for pre job assessments, which have the
objective of identifying and thereby avoiding safety hazards, on all
non routine work assignments. The supervisor must be present for the
start of the work to ensure compliance with the pre job assessment and
then must periodically monitor work progress.

3. Rewrite the Alcan Kingston Works Maintenance Department safety rules to
emphasize the safety precautions associated with stored energy be it
compressed air, steam, or hydraulic systems with accumulators. The
existing safety rules concentrate on electrical disconnects which must
be locked out before starting most maintenance projects.

4. Provide a standard practice for working on compressed air and steam
piping systems. The standard practice must stress the need to properly
relieve the stored energy in piping systems.

5. Install valves for relieving pressure adjacent to the isolating valves
in the compressed air piping system. This would allow the compressed
air supply to be shut off and the pressure then relieved at the same
location without having to follow the pipeline to find a suitable
relieving valve.

6. Design and fabricate portable guards to support the piping on either
side of a Victaulic coupling should the compressed air piping need to
be disassembled in future. Piping supports/guards will be required for
both eight inch and six inch piping.

The accident investigation also revealed several deficiencies that while
they were not a factor in this accident could lead to future safety
problems if not corrected. Recommendations to correct these safety
concerns are as follows:

1. Implement a strict safety procedure for the proper locking out and
tagging of piping system valves. This procedure must include not only
valves closed for safety reasons but also valves that must be left open
for safety reasons such as valves opened to relieve pressure.

2. Prepare specifications for new valves to include provisions for proper
lockout. Most gate and globe valves can only be locked by wrapping
chain around the valve body and through the handle.

3. Change the main isolating valves in the compressed air piping system
from butterfly to gate valves. Any movement of a closed quarter turn
butterfly valve handle will result in some leakage.

4. Install a compressed air dryer in North Plant to minimize the buildup
of ice in the compressed air piping thereby reducing the possibility of
maintenance being required on the compressed air piping.

5. Identify all compressed air and steam piping as to contents and
direction of flow.

COMMENTS ON RECOMMENDATIONS BY CORONER:

An inquest was held concerning this industrial death. The verdict of the
Coroner's Jury was the Egon B. Holterman's death was accidental. The jury
made three recommendations.

Recommendation No. 1:

As a result of this death there was, over and above the Coroner's
investigation, and investigation by the Department of Labour, Alcan's own
internal investigation, and an investigation by the union representing the
employees of Alcan. Recommendations in Exhibit 5 were the combined efforts
of Labour and management.

The Jury really did not feel that they could suggest anything better, and
recommended that Exhibit 5 be accepted as a recommendation in its totality.
(See attached Exhibit 5.)

I might add that the recommendations listed, some six numbered, are
self-explanatory.

Recommendation No. 2

I might add here that Alcan already has an in-plant safety coordinator.
However, the Jury felt that there would probably be small plants who would
be handling compressed air who did not have in-plant safety coordinators.
They, therefore, made Recommendation 2.

Recommendation No. 3

The Jury simply felt that the colour-coding system might help identify
lines in different locations as the their content.

As author of the above, I certainly feel that if the recommendations
proposed by this Coroner's Jury were followed there would be no repeat of
this particular type of accident.