|
|
Record Number: |
2063 |
CIS Descriptors: |
INSTALLATION OF PIPE SYSTEMS
MANUFACTURING INDUSTRIES
BURSTING
|
|
-
REPORT CHARACTERISTICS:
DONOR: Office of the Chief Coroner
JURISDICTION: Ontario
REPORT TITLE: Verdict of Coroner's Jury
INDIVIDUAL PRESIDING: Dr. C. R. Meyer, Coroner
PLACE OF INQUIRY: Frontenac County
DATE OF INQUIRY : 1988-05-25
INFORMATION ABOUT DECEASED:
NAME: Egan B. Holterman
OCCUPATION: Pipefitter
INDUSTRIAL SECTOR: Metal Manufacturing
ACCIDENT INFORMATION:
DATE OF FATALITY : 1987-12-07
PLACE OF ACCIDENT: Kingston Alcan Works North Plant
BRIEF CAUSE OF DEATH: Exsanguination; ruptured aorta; multiple
internal
injuries; laceration of the liver and spleen.
BRIEF MANNER OF DEATH: Explosion: hit by eight inch pipe in
the chest.
ACCIDENT DESCRIPTION:
Kingston Alcan Works was comprised of several plants. The plants
of
concern to us in the present investigation are the North plant
and the
South plant. Closure of the South plant took place in April
1987.
These plants were connected by a pipe line which carried compressed
air
from the North plant to the South plant. It is an above ground,
eight
inch aluminum pipe line which is under pressure 90 to 100 pounds
per
square inch of compressed air.
The 7th day of December 1987 this line was still live even though
the
South plant was closed, because it was necessary that new boilers
and
air compressors had to be installed in the North plant. They
were
finally commissioned on November 1, 1987.
On Thursday, December 3, 1987, Mr. James Latimer, the Contractor
Engineer at Alcan, decided the eight inch pipe line was no longer
needed. He advised Mr. Walter Hodgins, the Central Maintenance
foreman, that he could shut off the compressed air supply to
the South
plant complex. This could be done safely by:
1) Shutting off the compressed air supply to the line by closing
the
valve at the North plant.
2) Bleed off the air which was locked in the eight inch line.
3) Separate the pipes and install the cap.
It was decided that the person who should do the job would be
Egan
Holterman.
Egon Holterman, 51 year old pipefitter, had worked for Alcan
for
approximately twelve years. It was felt that he would have as
much
knowledge about the workings of the pipe lines as anyone in
the
Kingston plant.
Shortly after 2:00 pm on December 7, 1986, Mr Frank Maloney,
a
Stationary Engineer at Alcan, met Mr. Holterman in the North
plant to
assist him with the job. Mr. Maloney used a ladder to climb
to the
shut off valve just outside the North plant. The valve was hard
to
turn because it had been in the open position for a long time.
Mr. Holterman and Maloney then proceeded to the area of the
pipe line
where the blank was to be installed. Mr. Holterman sprayed WD-40
on
the flange bolts which held the pipes together and at which
joint the
blank was to be inserted. He then moved to the next joint, which
was
one side of the expansion joint, which in this pipe line is
shaped like
a U. He loosened the nuts and bolts on the flange but nothing
happened. Mr. Maloney reached to get a hammer from the tools,
and as
he did so, there was a loud explosion.
As a result of this explosion Egon Holterman was struck by the
eight
inch pipe in the chest. He was rushed to the hospital, and died
on the
OR table.
RECOMMENDATIONS ISSUING FROM INQUIRY:
1. This jury agrees with the recommendations submitted by management,
Union and Department of Labour as stated in Exhibit 5 and would
recommend immediate implementation.
2. Appoint an in-plant safety coordinator to ensure that safety
procedures
are followed at all times. Such procedures to include proper
job-related safety requirements.
3. We also recommend colour-coding as to content, of all piping
systems in
conjunction with recommendation no. 5, page. 5.
Alcan Recommendations
Recommendations to change equipment, safety rules and operating
procedures
all aimed at reducing or eliminating the possibility of repeating
this
accident were submitted both by members of the accident investigating
committee and by other innovative, safety conscious Alcan employees.
These
recommendations are as follows:
1. Communicate to all tradesmen the hazards of stored energy
particularly
those associated with compressed gases. Dupont and Alcan Oswego
will
be contacted for safety programs concentrating on stored energy.
2. Re emphasize the requirement for pre job assessments, which
have the
objective of identifying and thereby avoiding safety hazards,
on all
non routine work assignments. The supervisor must be present
for the
start of the work to ensure compliance with the pre job assessment
and
then must periodically monitor work progress.
3. Rewrite the Alcan Kingston Works Maintenance Department safety
rules to
emphasize the safety precautions associated with stored energy
be it
compressed air, steam, or hydraulic systems with accumulators.
The
existing safety rules concentrate on electrical disconnects
which must
be locked out before starting most maintenance projects.
4. Provide a standard practice for working on compressed air
and steam
piping systems. The standard practice must stress the need to
properly
relieve the stored energy in piping systems.
5. Install valves for relieving pressure adjacent to the isolating
valves
in the compressed air piping system. This would allow the compressed
air supply to be shut off and the pressure then relieved at
the same
location without having to follow the pipeline to find a suitable
relieving valve.
6. Design and fabricate portable guards to support the piping
on either
side of a Victaulic coupling should the compressed air piping
need to
be disassembled in future. Piping supports/guards will be required
for
both eight inch and six inch piping.
The accident investigation also revealed several deficiencies
that while
they were not a factor in this accident could lead to future
safety
problems if not corrected. Recommendations to correct these
safety
concerns are as follows:
1. Implement a strict safety procedure for the proper locking
out and
tagging of piping system valves. This procedure must include
not only
valves closed for safety reasons but also valves that must be
left open
for safety reasons such as valves opened to relieve pressure.
2. Prepare specifications for new valves to include provisions
for proper
lockout. Most gate and globe valves can only be locked by wrapping
chain around the valve body and through the handle.
3. Change the main isolating valves in the compressed air piping
system
from butterfly to gate valves. Any movement of a closed quarter
turn
butterfly valve handle will result in some leakage.
4. Install a compressed air dryer in North Plant to minimize
the buildup
of ice in the compressed air piping thereby reducing the possibility
of
maintenance being required on the compressed air piping.
5. Identify all compressed air and steam piping as to contents
and
direction of flow.
COMMENTS ON RECOMMENDATIONS BY CORONER:
An inquest was held concerning this industrial death. The verdict
of the
Coroner's Jury was the Egon B. Holterman's death was accidental.
The jury
made three recommendations.
Recommendation No. 1:
As a result of this death there was, over and above the Coroner's
investigation, and investigation by the Department of Labour,
Alcan's own
internal investigation, and an investigation by the union representing
the
employees of Alcan. Recommendations in Exhibit 5 were the combined
efforts
of Labour and management.
The Jury really did not feel that they could suggest anything
better, and
recommended that Exhibit 5 be accepted as a recommendation in
its totality.
(See attached Exhibit 5.)
I might add that the recommendations listed, some six numbered,
are
self-explanatory.
Recommendation No. 2
I might add here that Alcan already has an in-plant safety coordinator.
However, the Jury felt that there would probably be small plants
who would
be handling compressed air who did not have in-plant safety
coordinators.
They, therefore, made Recommendation 2.
Recommendation No. 3
The Jury simply felt that the colour-coding system might help
identify
lines in different locations as the their content.
As author of the above, I certainly feel that if the recommendations
proposed by this Coroner's Jury were followed there would be
no repeat of
this particular type of accident.
|
|
|