Record Number: 1861

FATALITY REPORT



REPORT CHARACTERISTICS:

DONOR: B.C. Coroner's Service
JURISDICTION: British Columbia
REPORT TITLE: Verdict of Coroner's Inquest
INDIVIDUAL PRESIDING: L. W. Campbell, Coroner
PLACE OF INQUIRY: Tumbler Ridge
DATE OF INQUIRY : 1986-12-09

INFORMATION ABOUT DECEASED:

OCCUPATION: Unavailable
INDUSTRIAL SECTOR: Mining
NAME: Confidential

ACCIDENT INFORMATION:

DATE OF ACCIDENT : 1986-02-05
PLACE OF ACCIDENT: Quintette Mine
BRIEF CAUSE OF DEATH: Closed whiplash injury to spinal cord, blow to the
head.
BRIEF MANNER OF DEATH: Blunt injury to the head.
ACCIDENT DESCRIPTION:
On February 5, 1986 at approximately 1310 hours the deceased was struck
on the shoulder and then on the lower left side of the head by a 4" weld
type pipe cap which separated under pressure from the accumulator of a
steam cleaning unit. This complete unit is housed in the van of a three
ton truck.

Some of the circulation pipes of the unit were frozen; the deceased and
a fellow worker were trying to get them thawed so they could clean some
heavy equipment near McConkey Pit at Quintette Mine.

Usually these lines would have anti-freeze pumped into them before a
shutdown or storage period to guard against freezing. On the fourth of
February, the day before the accident, it was decided to try an
alternate method of storage, i.e., instead of anti-freeze, the operators
blew the lines clear with air pressure.

This exercise proved unsuccessful because on the morning of February 5,
1986 the lines were frozen. This condition was not immediately
recognized and the diesel motor operating the pump was started. When no
fluid came out of the cleaning nozzles, the deceased got a small propane
torch and thawed the line from the water tank to the pump and
accumulator.

He then went outside to see if the nozzles would spray. They would not,
so he went back inside the van to open a bypass valve on the pressure
line which would reroute some of the pressurized fluid back into the
suction line from the tank and thus reduce some of the pressure in the
system. This would give him time to apply heat to some of the other
lines in an attempt to get the unit operable.

The diesel and pump were running during this elapsed time and under
normal conditions that would be OK because the pressure would be
controlled by the relief valve on the boiler. However, in the present
situation, with lines frozen between the accumlator and boiler, the
pressure in the accumulator rose very rapidly to dangerous levels.

As the deceased approached the unit, the pressure in the accumulator
reached a point high enough to blow the cap off. On hearing the
explosion, his fellow worker entered the van and found Daniel on the
floor in an unconscious state, so he called other workers nearby to get
help and call an ambulance.


RECOMMENDATIONS ISSUING FROM INQUIRY:

To: Boiler and Pressure Vessel Safety Branch, Ministry of Labour

1. All vessels and fittings in pressure system installations fall under the
Boiler and Pressure Vessel Safety Act regardless of size, and that the
following minimum recommendations be included in the regulations.

a) There be an unloader valve and pressure gauge installed after the pump
before any valves in the system.

b) There be a safety relief valve before any valves in the system.

c) That any alteration to the system requires the system to be re-certified.

d) That the owner must provide training to the operator to an acceptable
standard as set out by the Boiler and Pressure Vessel Safety Branch.

e) That the system be changed with glycol anti-freeze during shutdown in
freezing weather conditions.